Oversized cargo logistics - Mobilising a 98Te HLS Frame for shipment to Malaysia

MDL required a logistics partner capable of mobilising high-value, oversized equipment for onward shipment to Malaysia, while meeting strict vessel schedules and operational requirements. The cargo included a 98Te Horizontal Lay System (HLS) frame, used in the deployment and retrieval of subsea umbilicals in the offshore energy sector.
 

Given its scale and weight, specialist infrastructure, technical lifting expertise, and meticulous planning were essential to enable transport as a single piece. With the capability and capacity to deliver this, ASCO provided a fully integrated logistics solution that reduced handling complexity, transportation time, and overall project costs.

 

Perterhead mdl lift3 case study

Client

MDL

Type

Supply Bases, Lifting, Project Cargo, Transportation

Location

Peterhead, North Base

Perterhead mdl lift2 case study

At a glance

  • Mobilisation and loading of complex, high-value heavy cargo, including an HLS frame and supporting flex lay assets
  • Specialist heavy-lift operation delivered from Peterhead Supply Base - supported by dedicated lift supervisors, operational crews, and a 400t crane 
  • Cargo transported in one piece, reducing handling, permitting complexity, project time, and cost

Approach

ASCO combined technical heavy-lift planning, operational coordination, and project delivery expertise to manage the mobilisation from quayside to vessel. Lift plans were developed around the cargo’s dimensions and weight to ensure controlled handling throughout the operation.

At the Peterhead supply base, quayside infrastructure, experienced operational teams, and trusted specialist partners ensured the right equipment, transport capability, and resources were in place at the right time.

Safety remained central throughout, with robust planning, compliance procedures, and a strong HSE track record helping ensure the operation was delivered efficiently and without incident.
 

Impact

  • 98Te HLS frame successfully mobilised for onward shipment to Malaysia 
  • Up to 7 days saved by avoiding road transport permitting and movement orders 
  • Removed handling complexity and associated transport costs through single-piece mobilisation 
  • Delivered in full compliance with HSE, transport, and lifting regulations
     